{ Manoel Island Yacht Yard Upgrade }

As part of our ongoing commitment to upgrade our facilities extensive surfacing works are being carried out on our hardstanding areas.Phase I of the project was successfully completed in October 2011. Over 8,000 sq.m were surfaced using high strenght concrete.

Last August Phase II of the project commenced with a further 5,000 sq.m of concrete being laid. It is expected these works will be completed by end September 2012. This phase will convert over 80% of our hardstanding area into a safe and clean environment with the final part of the project being completed next Summer.